ADE Power Australia designed and manufactured a 16.5m long switchroom consisting of 5 separate rooms, including a switchroom, bathroom, control room, and battery room.

Overview

Flyers Creek is a 145 MW wind farm in Wiradjuri County, comprising of 38 wind turbines, a 33 kV power line, an on-site substation, a 132 kV power line, and a switching station connecting the project to existing power lines. The wind farm outputs ~450 GWh per year, powering ~80,000 homes.

Case Study PDF

Modular Switchroom – Flyers Creek Wind Farm case study in PDF for download.
The switchroom included: small light and power, HVAC, fire system, security system, and support structure.
ADE worked alongside PBE Rutherford for site installation and commissioning.
Fully integrated and comprehensive communication and automation systems allowing full diagnostics and remote operation.